A productive spring on the construction site with over 425 workers in action!
Here's a look at the work progress:
Pavilion A:
✅ 42 concrete slabs completed since the end of April
• Electromechanical work has begun
• Interior wall layout marking is in progress
• Exterior envelope work is scheduled to start in June
Pavilion B:
✅ 25 concrete slabs completed so far
• Construction is progressing using a step-by-step method
📸 Check out the progress photos below. 👇
Pomerleau
Québec Infrastructure Corporation